↘ GOMTI RIVER FRONT, LUCKNOW: In 2014-15, Rs 656 crore was allocated, which escalated to Rs 1,513 crore. By March 2017, despite 95 per cent of the amount being spent, only 60 per cent of the work was completed. A CBI probe is blamed for the tardy progress
↘ SUPERSPECIALITY HOSPITAL, SAIFAI: The state’s largest super-speciality hospital with 500 beds was planned in 2014 for Rs 333 crore, which later escalated to Rs 537 crore. In March, CM Yogi inaugurated it, but due to unfinished work and pending machine installations, services haven’t started
↘ GUEST HOUSE, SAIFAI: Construction began in 2015 for the 100-room project at Rs 42 crore. In 2017, 90 per cent of the work was complete but is now stalled
↘ CRICKET STADIUM, SAIFAI: Construction was completed in…